WRBorger Refinery: Gasoline Benzene Reduction,
Heat Integration
back to Projects index
| Client |
Wood River - Borger
(CoP and
EnCana J.V.) |
 |
| Location |
Borger, Texas |
| Project |
Gasoline Benzene Reduction |
| Duration |
3Q2008 - 1Q2009 |
| Scope |
Major heat integration revamp,
reducing benzene to EPA limit |
| Role |
Systems Area Leader for three NGL distillation
units |
| Tasks |
- Close out Actions from PHA and LOPA of
assigned units
- Markup P&IDs with PHA actions for IFD, then
IFC release
- Completeness/consistency check of Systems
deliverables
e.g. Hydraulics, Control Valves and Flow Elements, PSVs,
Specialty Piping Items, Nozzle Connection Summary, Line Lists,
Tie-in Lists, Paint & Insulation, equipment DP/DT
- Weekly staff meeting with detailed agenda &
action plan
- Management of Change for P&IDs, Line List &
Tie-in List
- Facilitate interdisciplinary decisions on
e.g. thermosiphon
between Exchangers & Vessels, Control strategy between Process and
CSE Engineers, cross-consistency checks
|
|